Back to Plan Room
  Lima, OH Watermain
   
   
Bid Date: 7/10/2009; 10:00 a.m.
Last Modified Date: 6/26/2009
Atlas Estimator: Casey Dillon
Atlas Project Manager: Tom Morlan
Atlas Project Administrator: Elizabeth Golden
Specifications: Click here for specifications
Drawings: Click here for drawings
Bid Schedule: See specifications for bid schedule
Addenda: Click here for Addendum 1

Click here for Addendum 2

   
 Stormwater Pollution Prevention Specs: Click here for Stormwater Pollution Prevention Specifications
Stormwater Pollution Prevention Plans: Click here for Stormwater Pollution Prevention Plans
Traffic Control Plans: Click here for Traffic Control Plans
Project Location: Along Agerter Road from the Auglaize River (just west of Conant Road) to the southeast corner of Bresler Lake Reservoir (just west of Kemp Road)
Bid Hold Period: 60 days
Project Duration: 570 days
Liquidated Damages: $800
Tax Exempt: Yes